Politics Controversies Trail Vice President's N7Billion Official Residence In Abuja

P

PressRoom

Guest
In eight years, about N6.215billion has already been spent on the new official residence of the nation’s Vice President in Abuja, but the project remains engulfed in controversy, investigation by The Nation reveals.

While the House of Representatives Committee on FCT is alleging that the job done does not commensurate with the 87 percent of the contract sum paid, no one seems to know when the project will be ready for occupation.

The project has been abandoned in the last five years owing to disagreement between the Senate and the Federal Capital Development Authority on the variation of the project. The contract was awarded in 2009 at a cost of N7billion but N6.215 billion was paid to the contractors. A year by calculation that had erstwhile President Goodluck Jonathan in power.

upload_2017-1-15_7-54-2.png


In 2012, the immediate past Minister of the FCT, Senator Bala Mohammed, submitted a request for additional N9billion to complete the project.

The Nation learnt that although the Bureau of Public Procurement (BPP) reduced the variation cost to N6billion, the 7th Senate rejected it following an intelligence report that “the request for the additional cost was suspicious.”

The complex is made up of the followings: VP’s ADC’s house (N258m); Chief Security Officer’s house (N228m); mosque (N95m); Church (N84m); security quarters, (N114 m); boys quarters( N288m); Gate House(N55m); infrastructure (N1.7 billion), among others.

While the government was trying to find solution to the contract stalemate, a fresh row is trailing the new residence.
The row borders on:
• Suspected inflation of the cost
• Job done allegedly not commensurate to the 87 percent payment of the contract sum
• Why did the construction company only ensure 50 per cent completion of project after 87 per cent payment
• Alleged outrageous request for variation of the project
*Lack of timeframe for the completion of the residence

The Chairman of the House Committee on FCT, Hon. Herman Hembe, who spoke with journalists yesterday, said his committee was disappointed at the way the contract was being managed.
Hembe said: “In all, about 87 percent of the contract sum has been paid. You can go and take a look and say by yourself if the work done is commensurate with the funds so far paid.
“The committee has severally expressed disappointment over this very sad situation.”

A top source said: “We are suspecting underhand dealings by some key officials in the past administration of ex-President Goodluck Jonathan.

“Initially, a variation of N13billion was proposed but public outcry forced them to reduce it to N9billion before the BPP scaled it down to N6billion.

“Also, the job done is about 50 percent but 87 percent payment of the contract sum was effected.
“As I am talking to you, nobody knows the time frame for the completion of the project. And when the 87 percent payment was done, the agreement included furnishing materials. But we learnt the contract scope has been altered.

“Already there is provision for the project in 2017 budget but the administration of President Muhammadu Buhari should take more than a passing interest in the residence. The project is being turned into a goldmine by some officials. Let there be a comprehensive audit of the extent of work in line with the contract terms.”

“Again, the government cannot abandon the project after attaining about 50 percent completion. But the resources are not just there now. The only option is the completion of the project in phases.

Responding to a question, the source added: “The nation has about 19,000 projects abandoned in the last 42 to 43 years. We may need about N12trillion to complete these projects, including the new residence of the Vice President.

“Some people are even suggesting that the project should be converted to either a hospital or an office space for any of the security agencies.”
 